Plastering covers rough walls and uneven surfaces with a plastic material called plaster or mortar, giving masonry a smooth, durable face ready for paint or wallpaper. The same process is called rendering when the coating goes on exterior walls, where it protects the masonry from rain, heat, and other weather. The coating is only as good as the structure behind it: a settling foundation cracks fresh plaster within weeks, so foundation repair work such as underpinning methods should be finished first. Once the substrate is stable, the plastering method decides how flat, strong, and long-lasting the finish will be.
Every plastering job shares the same anatomy: background preparation, control points, one to three mortar coats, and curing before decoration. The sections below cover each method, the thicknesses and mixes that go with them, and the checks that separate a wall that stays true from one that drums and cracks.
The Plastering Process and How It Works
Plastering follows a fixed sequence no matter how many coats are specified. The background is cleaned, small mortar pads called dots are set to control thickness, screeds are run between the dots, and mortar is applied in layers with specific jobs. The full plastering process balances three goals: covering surface irregularities, building a level plane, and delivering a smooth face that will not crack or blow. Skipping a coat to save time shows up later as a wavy or hollow wall.
Dots and Screeds Set the Standard
Flatness is not left to the eye. The plasterer prepares dots of mortar, typically 150 x 150 mm and about 10 mm thick, at a low level on the wall. Those dots are transferred upward with a plumb bob so upper and lower dots fall in the same vertical plane, and more dots are added at 1500 to 2000 mm spacing. Screeds, strips of mortar run between the dots, act as gauges; plaster is struck off against them so the finished face follows the true plane.
Coat Systems at a Glance
| System | Number of coats | Typical total thickness | Best use |
|---|---|---|---|
| Single-coat | 1 | 10 to 12 mm | Low-cost work, outbuildings |
| Two-coat | 2 | 12 to 15 mm | Standard interiors on true walls |
| Three-coat | 3 | 21 to 26 mm | High-quality finishes, uneven backgrounds |
| Plaster on lath | 2 to 3 | Varies with lath | Ceilings, timber partitions |
Preparing the Background: Dots, Screeds, and Levelling
The background must be ready before the first trowel of plaster touches the wall. Loose material, dust, grease, and efflorescence are removed, and very smooth concrete is hacked or treated with a bonding agent so the mortar can grip. The wall is wetted first so it does not draw water out of the mix too quickly. Checking that the wall face is truly vertical is a levelling exercise at building scale, and the same levelling methods used in surveying apply when reference heights move across a site.
Setting Dots Step by Step
- Clean the wall and wet it thoroughly.
- Prepare a stiff mortar that will hold its shape without slumping.
- Press the first dots onto the wall, 150 x 150 mm and about 10 mm thick.
- Transfer the dots upward with a plumb bob so upper and lower dots align in one vertical plane.
- Add intermediate dots across the surface at 1500 to 2000 mm spacing.
- Run screeds between the dots and allow them to stiffen before plastering.
- Apply the mortar and strike it off against the screeds.
Levelling the Wall Face
A plumb bob checks vertical alignment dot to dot, while horizontal level is checked with a spirit level, a water level, or a laser line on long runs. Corners and reveals get extra attention because an opening that is out of square is impossible to hide once the plaster dries. The levelling done here decides how straight every shadow line in the finished room will be.
Three-Coat Plastering: Rendering, Floating, and Finishing
Three-coat plastering is the traditional specification for high-quality work. The first coat is the rendering coat, the second is the floating coat, and the third is the setting or finishing coat. The rendering coat is scratched to key the next coat, the floating coat brings the wall to an even surface, and the finishing coat provides the smooth painted face. Where a wall needs a heavier, more textured surface than plaster can deliver, natural stone cladding is a durable alternative.
The Rendering Coat
The rendering coat is dashed onto the wall with a mason’s trowel and worked into the joints and across the surface. Its thickness covers all inequalities of the background, normally about 12 mm. It hardens slightly, then scratch marks are made with the trowel ledge to key the next coat, and the surface is left to dry completely.
The Floating Coat
The first coat is prepared for the second by clearing dust and wetting it properly. Strips about 10 cm wide, or patches of 15 x 15 cm, are applied as gauges for the thickness of the floating coat. Mortar is dashed on with the mason’s trowel, spread, and rubbed to a plain surface with a wooden float, then beaten with the float edge. The floating coat is 6 to 9 mm thick and dries completely before finishing.
Gauges Control the Floating Coat
The strips and patches fix the thickness so the coat cannot drift thicker in one corner and thinner in another. Beating with the float edge consolidates the mortar and closes hairline voids.
The Finishing Coat
The finishing coat goes on after the floating coat has stiffened, typically about six hours later on lime work. For lime-sand mortar, a cream of lime and sand in a 4:1 ratio is applied with a steel trowel, rubbed, and finished smooth. Rubbing continues until the coat is dry; curing begins one day later and runs for seven days. Cement work gets a thin cement-sand coat travelled to a hard face.
| Coat | Order | Thickness | Purpose |
|---|---|---|---|
| Rendering coat | First | About 12 mm | Cover inequalities, provide a key |
| Floating coat | Second | 6 to 9 mm | Bring the surface to an even plane |
| Finishing coat | Third | 2 to 4 mm | Smooth face ready for decoration |
Two-Coat and Single-Coat Systems
Two-coat plastering applies a rendering coat followed directly by a finishing coat, skipping the floating stage. The joint between the coats is scratched to provide a key, and the finish is worked thinner than in three-coat work. The method suits walls that are already reasonably true. Single-coat plastering applies one coat of a richer mix for outbuildings and surfaces later covered by tiles or panelling. Whatever the system, the geometry depends on measurement: dot spacing, coat thickness, and screed positions are set out with tape, the same discipline surveyors apply when they use direct methods of linear measurement in surveying.
Two-Coat Plastering
The rendering coat is applied, scratched, and allowed to dry. The finishing coat goes on directly, usually a slightly richer mix, and is travelled smooth. Without a floating coat to absorb errors, the background must be straighter. Two-coat work is common on blockwork interiors laid to line and level.
Single-Coat Plastering
A single coat is laid on at 10 to 12 mm, struck off to the screeds, and finished in one pass. The mix is richer than a rendering coat so it does the work of both body and finish. Expect a less perfect plane than floated work, and avoid single-coat plaster on exterior walls. It is a pragmatic finish for garages, workshops, and re-skimmed ceilings.
Plaster on Lath
Plaster on lath is an older method in which thin strips of wood or metal are fixed across framing and plaster is forced through the gaps so keys on the far side hold the coat in place. The method still appears in renovation work, and the practical steps of mixing, applying, and finishing follow the sequence described in the step-by-step plastering process and tips at ConstructUpdate.
Wooden Laths
Wooden laths are thin strips nailed to studs or joists with a small gap between them, usually 6 to 10 mm. The first coat is pressed through the gaps to form keys that lock the plaster to the lath. The surface is scratched, and the finish goes on after the first coat dries. Timber laths suit dry interiors but move with humidity.
Metal Laths
Metal laths, expanded metal or welded mesh, are fixed over the framing and plastered the same way. The mesh provides a stronger key than timber and does not swell or shrink. Metal lath is the standard choice for repair work over old ceilings and curved shapes.
Keys Are the Secret
The key is the portion of plaster that pushes through the lath and spreads on the far side. It is the entire mechanical connection between the coat and the structure, so the first coat must be pressed through firmly, not merely trowelled onto the face. Weak keys mean hollow plaster that eventually falls away.
- Fix laths across the framing with the correct gap
- Dash the first coat through the gaps to form keys
- Scratch the surface and allow it to dry
- Apply the second coat and rule it flat
- Finish smooth and cure as with any plaster
Curing, Inspection, and Quality Control
Plaster keeps hardening after the trowel work stops, and curing controls how. Lime finishes are wetted one day after application and kept damp for seven days; cement finishes benefit from the same regime in hot weather. Plaster that dries too fast loses strength and shrinks into a web of hairline cracks.
Inspecting the Finished Surface
After curing, tap across the wall with a coin or trowel handle. A solid ring means the coat is bonded; a hollow, drumming note means it has lost contact with the background. The check is known as sounding the surface, and it works on the same principle as locating soundings in hydrographic surveying, where reflected signals reveal what lies beneath. Cut out hollow patches and make them good before painting.
Curing Schedules
- Lime finish: damp one day after application, keep damp for seven days
- Cement finish: keep damp for at least seven days, longer in hot or windy weather
- Lath work: cure the first coat before applying the second
- Painted finishes: allow two to four weeks of drying before painting
Planning and Control on Site
Good plastering starts before the first dot is set. Walls are checked for plumb and square, the background is assessed for suction and soundness, and the coat system is matched to the budget and substrate. On larger sites the logic that surveyors use to close a control network applies: the types of traverse and methods of traversing keep a grid consistent across a building, so reference points are checked before work begins.
